Optimization of the district heating systems in the city Oleksandriia

Oleksandriya city
Kirovohrad Region
District heating
preparation

Estimated cost

20 880 000 EUR

Brief description:

The Project  provides a total heat system reconstruction of Oleksandriya city central part (80% of a total city consumption) with moderate heat system decentralization and implementation of modern energy efficiency equipment.

The heat system decentralization predicts heat energy source relocation closer to consumers, into exist heat substations, which located in the middle of residential areas and which will be rebuild to the submain boiler houses with small capacity.

It provides with a reduction of heat losses in distribution pipeline up to 4-5 % by reducing capacity, reducing of diameter and especially by high heat insulation material parameters of polyurethane foam. During heat substation reconstruction to submain boiler houses, predicts to install modern energy efficiency equipment and to perform other measures listed below.

The Project provides a construction of 24 submain boiler houses, middle and high pressure gas distribution pipelines, heat system renovation on preliminary isolated ones. Such construction is previously agreed by a relevant decision of Oleksandriya city council.

Beneficiary:

PUC “Teplokomunenergo”

Similar Projects

Rehabilitation of street lighting in Dnipro (former Dnipropetrovsk)

Replacement of technologically and physically obsolete lamps with incandescent with mercury arc lamp DRL, high-pressure sodium arc lamps with LED lamps of 42 W, 139 W. Reconstruction of cable-air lines with the use of the latest technologies (isolated wires). Energy savings expected up to 50% of...

Rehabilitation of the outdoor lighting systems with introduction of Energy Efficient technologies in Kamyanske (former Dniprodzerzhynsk)

The Project  aimed on the increasing of the level of social comfort in the city and reducing of the harmful impact on the environment by reconstruction of the lighting system. The Project  consists of: Rehabilitation of 53 chains of the street lighting using the energy efficiency technologies and automatic systems; Installation of 17 traffic lights with automatic...

Thermal renovation of public healthcare buildings of Volyn oblast

The Project  involves 64 buildings with next EE measures implementation: Conducting of building’s’ walls thermal renovation. Windows and doors replacement on energy saving ones. Lightning system modernization in buildings. Integration of energy consumption monitoring system on daily base. Integration of heating regulation system according to weather and...

Construction of new Deyiv Hora landfill facility and Improvement of solid waste management in the city Kremenchuk

The Project provides for the construction of solid waste sorting line with the annual capacity from 50 to 100 thousand tons. Waste recycling will include the following equipment: loading conveyor, sorting platform, sorting conveyor, separating drum, overload conveyor, reverse conveyor, belt that delivers valuable resource faction in automatic press, automatic press, storage...

Thermomodernization of the public buildings in Zaporizhzhia

Thermomodernisation of 14 buildings of public healthcare sector and 46 buildings of public education sector Activities include: insulation of exterior walls, replacement of windows and doors, insulation of roofs, insulation cap, insulation ceiling basement, restoration of drainage system, installation of local ventilation systems with heat recovery, reconstruction of the...